Coming soon: more accessible parking lots and an outdoor science park!

UO Athletics is constructing a new indoor practice field next to Autzen Stadium and will be relocating their two outdoor practice fields south of their current location. To accommodate this, Leo Harris Parkway will be re-routed to the south and the existing City-owned paved parking lot serving Eugene Science Center, Cuthbert Amphitheater, and Alton Baker Park guests will be relocated to two new parking lots east and north of Eugene Science Center. The lot south of the science center will accommodate staff. 

Visit THIS PAGE for information about UO Football Tailgating at the science center.

Construction Timelines

Timelines are subject to change, but we will attempt to keep these as up to date as possible.

MLK Jr. Blvd

ActivityStart DateEnd DateImpact
Partial closure of two East bound lanes3/1/248/12/24Two West bound lanes will be split into single East and West bound lanes.
West intersection of MLK Jr Blvd and Leo Harris Pkwy Closed6/11/248/12/24Access to ESC is only through the East intersection of MLK Jr Blvd and Leo Harris Pkwy

Areas Surrounding Eugene Science Center

ActivityStart DateEnd DateImpact
PHASE 1
Construction fence installation2/5/242/8/24Blocks off access to north and east fields, and rear loading area.
Clearing, grading, trenching3/8/245/9/24Noise, but with cool vehicles, tools, and engineering principles.
Concrete, landscaping, paving5/10/246/14/24Temporary relocation of entrance and admissions - location to be announced.
Striping, lighting, finishing6/10/247/29/24Eager anticipation of new amenities!
PHASE 2
Leo Harris Parkway reconfiguration12/2/246/18/25Access to ESC lots will be through east intersection of MLK and Leo Harris.
Landscaping and irrigation6/12/259/19/25Eager anticipation of ESC construction being finished!