Skip to content
We are currently closed.Open Today: 10:00 am - 5:00 pm

Leo Harris Parkway scheduled to be shifted south after the UO football season.

UO Athletics is constructing a new indoor practice field next to Autzen Stadium and will be relocating their two outdoor practice fields south of their current location. To accommodate this, Leo Harris Parkway will be re-routed to the south and the existing City-owned paved parking lot serving Eugene Science Center, Cuthbert Amphitheater, and Alton Baker Park guests will be relocated to two new parking lots east and north of Eugene Science Center. The lot south of the science center will accommodate staff. 

Visit THIS PAGE for information about UO Football Tailgating at the science center.

Construction Timelines

Dates and timelines are subject to change, but we will attempt to keep these as up to date as possible.

ActivityStart DateEnd DateImpact
PHASE 1COMPLETED!New and more accessible parking lots for science center guests
PHASE 2
Leo Harris Parkway reconfiguration12/2/246/18/25Access to ESC lots will be through east intersection of MLK and Leo Harris.
Landscaping and irrigation6/12/258/31/25Eager anticipation of ESC construction being finished!
Back To Top